Hot Tapping Case Study: Jaguar Land Rover

HOT TAPPING CASE STUDY

JAGUAR LAND ROVER

Client:  Webber N.W Ltd, on behalf of Jaguar Land Rover 

The Problem:


Webbers were required to tap into a 6” cooling water main to supply new machinery.   


However, the water main could not be isolated or drained down because the system was constantly in use. 


Being a long-term client of Ormond hot tapping services, Webbers contacted us to do a under pressure drill on water. 


Our solution: 


Ormond shaped a 4” saddle and welded it on to the 6” water main. 


After successfully pressure testing the new connection, Ormond attached the under-pressure drill and began hot tapping the live water main. 


Once the hot tapping was complete, Ormond installed a safety blank to prevent leaving an open end. 


Tasks Involved:


  1. Pressure test 
  2. Hot tapping/under pressure drilling
  3. Welding
  4. Commercial Pipework
by PETER JAMES 2 January 2025
HOT TAPPING CASE STUDY
by PETER JAMES 2 January 2025
UNDER PRESSURE DRILLING CASE STUDY
by PETER JAMES 2 January 2025
HOT TAPPING CASE STUDY
by PETER JAMES 2 January 2025
GAS INSTALLATION CASE STUDY
by PETER JAMES 2 January 2025
MDPE INSTALLATION CASE STUDY
by PETER JAMES 23 September 2024
LINE STOPPING CASE STUDY
by PETER JAMES 2 July 2024
HOT TAPPING CASE STUDY
by PETER JAMES 12 June 2024
HOT TAPPING CASE STUDY
by PETER JAMES 12 June 2024
HOT TAPPING CASE STUDY
by PETER JAMES 12 June 2024
COMMERCIAL GAS PIPEWORK INSTALLATION CASE STUDY
More posts

Get A Quote Now

Describe your project requirements via the form below:

Instant Quotes  |  Free Site Visits  |  Competitive Prices

Call Now: 07917-667-450

Share by: