Hot Tapping Case Study: Chesterfield Hospital

HOT TAPPING CASE STUDY

Chesterfield Hospital

Client: Yorkshire Plumbing & Heating Services (YPHS), on behalf of Chesterfield Hospital 


YPHS and Chesterfield Hospital have trusted Ormond Pipework for our services in commercial & industrial gas pipework.   


The problem:


Chesterfield hospital acquired new gas fired boilers to power their heating system.   


To feed the boilers, new branches on their 6” existing
underground MDPE gas installation were required. 


The gas supply was constantly in demand, therefore it could not be shut off and the works had to be done live. 


Ormond were brought in to do one 3”
hot tapping on to a 6” MDPE gas supply.     

 

Our solution: 


Ormond attached a hot tapping clamp to the existing gas pipework. 


After a successful
pressure test, we began to under pressure drill the new branche. 


Once the live tapping was complete, a safety blank was attached to the valve. 


Hot tapping the connection avoided plant downtime and gas purging, which saved time and expense. 


Tasks involved:


  • Hot tapping / under pressure drilling
  • Live tapping on MDPE gas installation
  • Underground MDPE commercial gas pipework 

by PETER JAMES 23 Sept, 2024
LINE STOPPING CASE STUDY
by PETER JAMES 23 Sept, 2024
HOT TAPPING CASE STUDY
by PETER JAMES 02 Jul, 2024
HOT TAPPING CASE STUDY
by PETER JAMES 12 Jun, 2024
HOT TAPPING CASE STUDY
by PETER JAMES 12 Jun, 2024
HOT TAPPING CASE STUDY
by PETER JAMES 12 Jun, 2024
COMMERCIAL GAS PIPEWORK INSTALLATION CASE STUDY
by PETER JAMES 21 Mar, 2024
HOT TAPPING CASE STUDY
by PETER JAMES 21 Mar, 2024
HOT TAPPING CASE STUDY
hot tapping case study
by PETER JAMES 05 Mar, 2024
HOT TAPPING CASE STUDY
by PETER JAMES 10 Jan, 2024
LINE STOPPING CASE STUDY
More posts

Get A Quote Now

Describe your project requirements via the form below:

Instant Quotes  |  Free Site Visits  |  Competitive Prices

Call Now: 07917-667-450

Share by: