Client: Naylors, Barnsley


About:  Long-established British manufacturer of drainage products for the construction and retail industry, Barnsley based Naylors is a trusted client of Ormond Pipework Services. 


The problem: 

Alterations to our client’s factory deemed an existing gas main to be decommissioned for demolition. In addition, a new gas installation up to 200 meters of 6-inch mild steel pipe was required to supply a Kiln.


Our solution:

As an experienced Gas Safe registered company, Ormond used nitrogen gas to purge out the existing main. Our gas engineers then provided a decommission certificate, confirming to the demolition team it was safe to remove the old gas pipework. 


Hot tapping onto a 10-inch main was used to connect the new 6-inch gas installation to the Kiln. Hot tapping avoided any system downtime and reduced costs because gas to the rest of site could remain live. 


Once the general gas pipework was complete, a gas tightness test was performed. After a successful test, we did a direct purge of the new gas installation and produced a Gas Safe certificate. 


Procedures involved:

  • Hot tapping
  • Welding
  • Indirect gas purging using nitrogen 
  • Direct gas purging 
  • Gas testing
  • Gas pipework installation 

PROJECT IMAGES

  • commercial gas pipework installation

    Slide title

    Write your caption here
    Button
  • Slide title

    Write your caption here
    Button
  • Slide title

    Write your caption here
    Button
  • Slide title

    Write your caption here
    Button
  • Slide title

    Write your caption here
    Button
by PETER JAMES 2 January 2025
HOT TAPPING CASE STUDY
by PETER JAMES 2 January 2025
UNDER PRESSURE DRILLING CASE STUDY
by PETER JAMES 2 January 2025
HOT TAPPING CASE STUDY
by PETER JAMES 2 January 2025
GAS INSTALLATION CASE STUDY
by PETER JAMES 2 January 2025
MDPE INSTALLATION CASE STUDY
by PETER JAMES 23 September 2024
LINE STOPPING CASE STUDY
by PETER JAMES 23 September 2024
HOT TAPPING CASE STUDY
by PETER JAMES 2 July 2024
HOT TAPPING CASE STUDY
by PETER JAMES 12 June 2024
HOT TAPPING CASE STUDY
by PETER JAMES 12 June 2024
HOT TAPPING CASE STUDY
More posts

Get A Quote Now

Describe your project requirements via the form below:

Instant Quotes  |  Free Site Visits  |  Competitive Prices

Call Now: 07917-667-450

Share by: